Your team is two days from launching a critical subscription feature. QA uncovers a P1 bug affecting 8% of users that will take an extra 3-4 days to fix. How do you assess the situation and decide on the next steps?

Write your approach on PM Quest

Community approaches

Pavlo’s approach

The good news is that it's P1 not P0 😁 Since the feature is critical we can't ship it with bugs. Since there is a way to identify who will be affected by the bug, I would propose to do partial release for other 92% of users. If partial release isn't possible, then I would work with team to get all the details about the issue, including accuracy of the estimate. Then I would communicate the information to the stakeholders proposing to delay the release by 1-2 days.